How can I hard stop the emergency power supply system?

How can I hard stop the emergency power supply system?

Hard Stop Emergency Power Supply System 

If the Aurora Platform application maintains a run engine or test ATS command beyond the duration of an event, then follow these steps to disconnect the signal from the application. 

 

1.      Power down any specific ATS or Generator I/O by opening associated DC breaker or fuse. 

2.     Power down any specific gateway tied back to ATS or generator by opening DC breaker or fuse. 

3.     The relay will be de-energized, and the equipment affected will then follow the normal time out procedures.  Generators or ATSs may not immediately return to normal state. This could take as long as 60 minutes, depending on specific ATS or generator internal time delays. 

4.     Call Customer Support at 1-888-234-3212 opt 2 before re-energizing the emergency power supply system equipment.  We will be able to walk you through the steps to get the application and equipment back to a ready state.


    • Related Articles

    • How to run a test when initiating commands from the equipment

      How to run a test when initiating commands from the equipment: While on the EPMS screen and viewing a system, select the Start Event button and the platform displays the Event Setup Wizard EPMS – Start Event Select the Test Type of Manual Config in ...
    • How to run an Auto Load Test

      EMPS How to run an Auto Load Test: While on the EPMS screen and viewing a system, select the Start Event button and the platform displays the Event Setup Wizard. EPMS – Start Event Select the Test Type of Load in the description. Event Setup Wizard  ...
    • How to run a Manual Load Test

      EPMS How to run a Manual Load Test: While on the EPMS screen and viewing a system, select the Start Event button and the platform displays the Event Setup Wizard. EPMS – Start Event Select the Test Type of Manual in the description. Event Setup ...
    • How to run a Manual Load Test with User Interface Commands

      EMPS How to run a Manual Load Test with initiating commands from the user interface: While on the EPMS screen and viewing a system, select the Start Event button and the platform displays the Event Setup Wizard. EPMS - Start Event Select the Test ...
    • How to run multiple system tests

      How to run multiple system tests: While on the EPMS screen and viewing a system, select the Start Event(s) button in the upper right-hand corner and the platform displays the Event Setup Wizard. EPMS – Start Event Select the Test Type of Load in the ...